With the opening of the Northgate Interchange the City of Chubbuck wanted to release an update on the New Day Parkway extension project. Phase 1 and phase 2 are complete and ready for the opening of the Interchange. With cooperation between the City and the Idaho Transportation Department a temporary traffic signal will be installed at the intersection of Yellowstone, Siphon Rd., and New Day Parkway; until a permanent system will be installed with a future ITD project. Due to a Fort Hall Irrigation repair project in the winter of 2020 we have postponed Phase 3 until 2021. This delay will allow the City to coordinate with Fort Hall Irrigation and lower the cost of development. Phase 3 will widen New Day Parkway from Yellowstone to Whitaker Road which will include four traveling lanes, turning lanes, and walking/bike lanes on both sides of the roadway.

 