(Bannock County, February 3, 2026; Cover photo credit: Bannock County)

Bannock County Planning & Development Services is drafting a comprehensive Land Use & Development Ordinance to replace current zoning code.

What changes are being proposed?

Planning & Development aims to consolidate and modernize eight existing ordinances into a comprehensive Land Use and Development Ordinance (LUDO) for Bannock County. This ordinance will regulate zoning, land use, subdivision, and other key aspects of county planning.  [Note: Proposed changes may be read here.]

Goals:

  1. Enhance clarity, consistency, and enforceability
  2. Align with state and federal regulations
  3. Use the Comprehensive Plan to guide the ordinance

Public Input Opportunities

Upcoming Input Opportunities

Public Hearings | Late April – Early June

Public hearings are your chance to share feedback on the proposed ordinance draft. Hearing dates will be posted on bannockcounty.gov/ourfuture and shared through this email once scheduled.

Previous Input Opportunities

Thank you for being part of the process! Community input has guided this work from the beginning.

2022 – “Open Space/Subdivision Ordinance”

2023 – Land Use Ordinance

2025 – Land Use & Development Ordinance Update

What’s Next?

Projected Project Timeline

Phase 1: Draft Refinement & Analysis

January – Mid-February

  • Refine the initial draft
  • Incorporate public input and technical data
  • Conduct mapping and data coordination
  • Prepare a revised working draft

Phase 2: Legal Review & Advisory Workshops

Mid-February – March

  • Legal review and revisions
  • Advisory Committee, Planning Council, and Commission workshops
  • Prepare an updated draft based on feedback

Phase 3: Post-Workshop Revisions

Late March – Early April

  • Incorporate direction from workshops
  • Complete required legal and policy analyses

Phase 4: Public Hearing Draft Preparation

Mid-April

  • Finalize draft for public hearings
  • Complete maps and supporting materials

Phase 5: Public Hearings

Late April – Early June

  • Planning Council public hearing
  • Commission public hearing
  • Additional hearings if significant changes are required

Phase 6: Adoption & Publication

Mid-June – Early July

  • Final edits and legal review
  • Formal adoption
  • Publication and effective date