(City of Pocatello Press Release, October 28, 2026)
The City of Pocatello’s Hiline Road and Signalization Improvement Project is nearing completion, with temporary intersection closures scheduled through mid-November.
The north and south sides of the intersection at Hiline Road, Pearl Street, and El Rancho Boulevard are currently closed. Beginning Monday, November 2, the entire intersection will be closed for final roadway preparation and paving. Motorists should follow posted detours and expect delays. Pedestrian access will remain available throughout construction.
The project includes replacing the four-way stop with a traffic signal, adding turn lanes, widening portions of Hiline Road, improving storm drainage, and upgrading sidewalks and pedestrian ramps. These improvements will enhance safety, accessibility, and traffic flow.
Project design costs totaled approximately $164,000, funded through a combination of City funds, American Rescue Plan Act (ARPA) funding, and grants. The City contributed approximately $14,000, with ARPA and grant funds covering the remaining $150,000. Construction is fully funded by a $2 million Strategic Initiatives Grant awarded by the Idaho Transportation Department through its Local Transportation Grant Program, requiring no local funding match.
The roadway is expected to reopen mid-November, although some additional work may continue after traffic access is restored. The City of Pocatello appreciates the community’s patience and cooperation as crews complete the final stages of construction.
POCATELLO PROJECTS: pocatello.gov/1002/Projects
To learn more about the City’s long-term vision and Comprehensive Plan 2040, visit comprehensive-plan-2040-pocatello.hub.arcgis.com/.